Production of the Upper Trishuli 3A has been shut down for three hours after people climbed on the pole of the power transmission line. There is a pole of 220 KV transmission line from Upper Trishuli Three A Production House in Shanti Bazaar, Nuwakot to Kathmandu.

Vijay Kumar Mishra, Assistant Plant Chief of Upper Trishuli 3A informed that the production had to be stopped after a person who lost his mental balance climbed in Kakeni Gaonpalika-7 Budheni.

According to Mishra, production has stopped from 11:30 am. It was being produced at 60 MW full phase. We have been closed for three hours now, ”he said.

Rupak Khadka, Deputy Superintendent of Police, District Police Office, Nuwakot, said that an attempt was being made to bring him down as he had reached the power line. “It simply came to our notice then. Now the technicians are trying to get up and down on their own, ‘said Khadka.